Stanbic Bank
Stanbic Bank
Stanbic Bank
Stanbic Bank
24.7 C
Kampala
Stanbic Bank
Stanbic Bank
Stanbic Bank
Stanbic Bank

Construction works of Katosi water treatment plant at 95%

Must read

The Managing Director of National Water and Sewerage Corporation (NWSC) Dr. Eng. Silver Mugisha has revealed that Construction works of Katosi water treatment plant stands at 95%.

Works on the 240million litres per day water production plant are near completion with 5% of project works left. The new plant will serve over 7.5million people in Kampala, Wakiso and Mukono up to 2040.

Assessing the progress of works and ongoing system tests at the plant, NWSC MD Dr. Eng. Silver Mugisha said that water supply challenges in Kampala, Wakiso and Mukono districts will soon be history.

This follows 100% completion of the Katosi Water Treatment Plant civil works, commencement of system tests and final installations at the facility.

“We are happy with the progress made so far by the contractor and consultant. We experienced logistical challenges in the delivery of some plant components. However, the good news is, the remaining 1.5kms of the pipeline was delivered and a km has already been laid, with 500m to go.” Eng. Mugisha said

 Dr. Silver added that the critical path which included laying of a 1.4mm diameter water intake 500m into the lake has been completed.

“After testing the plant, we shall test the reservoirs at Nsumba, Ssonde and subsequently carry out pressure tests for the new 51kms Katosi-Kampala bulk transmission main. Upon completion of the system tests, we shall charge the new system and serve the population.”

He said the combined production from Ggaba and Katosi water works will address the water supply challenges in the Kampala Metropolitan service area; Mukono, Wakiso and Kampala.

- Advertisement -

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest article

- Advertisement -