The reconstruction of the Makerere main building will cost Shs20.5 billion, the Vice-Chancellor Professor Barnabas Nawangwe has revealed. The university handed over the building to Excel Construction Company on Monday this week.

“Excel Construction Company quoted Shs20.5 billion, which is close to their own estimate of about Shs21 billion. Excel Construction Company competed against M/S V-Con Construction (U) Ltd, Zhaughuo Oversees Construction Engineering Co Ltd, Krishna Construction Co. Ltd, Jiangsu CJI Uganda Co. Ltd, China Nanjing International Ltd, Scaffold Engineering and Amp Construction Ltd, Canaan Construction Co Ltd, Sadeem Al Kuwait and Reliable Engineering and Decor Ltd,” Prof. Nawangwe said.

Prof. Nawangwe went ahead to task the contractor to accomplish the reconstruction with in seven months.

“We gave instructions that the contractor should ensure the main work in [Makerere University’s] main building is completed by the date when we have the 100-year celebration climax (8th October 2022),” Prof Nawangwe remarked.

Fire gutted the iconic building popularly known as the Ivory Tower in 2020. After over a year, the university hopes that the old building will be demolished, a new structure set up and work completed by September 8, 2022, before the centennial celebrations. Cabinet resolved to reconstruct the building following recommendations made by a committee set up to assess the structural integrity of the structure.

As a result, the cabinet directed the Ministry of Finance to release Shs 21 billion as per the university estimate. While the exterior design for the new main building will remain intact, the interior will be redesigned. Engineer Christina Kakeeto, the Director of Estates and Works at Makerere University explained that the interior redesign is intended to accommodate modern facilities like lifts.

In addition, only a few departments will be housed at the new main building according to resolutions from the university council. These include the Office of the Vice-Chancellor and his deputies together with the University Secretary.

The rest of the departments like human resources, public relations and finance will find new office space. However, Nawangwe notes that while the Shs 20.5 billion is sufficient for the reconstruction, there would be a need for over Shs 4 billion for furnishing the new structure.

To raise money for refurbishing, the university is planning to launch a fundraiser among Alumni and well-wishers. Nawangwe notes when the main building was gutted by fire, only the Master Card Foundation raised US$1 Million which was put to aiding recovery from the fire.